Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: January 2013 – December 2013
Service Type: Construction Project

SCOPE OF WORK

Dust Collection System

  • Design, supply, manufacture, installation and commissioning of one (1) Reverse Pulse Baghouse Dust Collection system for the Coarse Ore reclaim tunnels. Works also included clean air ducting, silencer, discharge stack, fan and dirty air ducting.
  • Design, supply, manufacture and commissioning of dust disposal system. Works included, batching weight hopper with load cells, rotary valve, isolation valve, agglomeration unit and discharge conveyor.
  • Civil design and installation including geotechnical survey.
  • Design, supply, manufacture and installation of structural steel, stairs and access platforms.
  • Design, supply, manufacture, installation and commissioning of compressed air system for dust collection system. Works included compressors, driers, filters, air receivers, monitoring instrumentation and pneumatic controls.

Ventilation System

  • Decommissioning of existing cyclone scrubber and extraction fan.
  • Design, supply, manufacture, installation and commissioning of one (1) Ventilation System for the Coarse Ore reclaim tunnels.

PROJECT HIGHLIGHTS

  • In-house engineering design of dust collector, ventilation, compressed air, civil and structural works.
  • Baghouse capacity: 72,000 m³
  • Ventilation system capacity: 57,000 m³
  • Structural Steel pre-assembled in modules to reduce site installation time.

Elizabeth Quay Jetty

Client: Simmons Global
Location: Elizabeth Quay, Perth
Project Duration: June 2015 to July 2015
Service Type: Construction Project

 

READ MORE

BHP Newman Upgrade

Client: BHP Billiton Iron Ore Pty Ltd
Location: Newman - Western Australia
Project Duration: January 2010 – September 2012
Service Type: Construction Project

 

READ MORE

Rio Tinto Coarse Ore Stockpile Bag House

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: January 2013 – December 2013
Service Type: Construction Project

 

READ MORE

RTIO Stockyard Waterline Replacement

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: December 2014 – September 2015
Service Type: Construction Project

 

READ MORE

Upgrade Fire Hydrant System

Client: Synergy
Location: Synergy
Project Duration: March 2014 – June 2014
Service Type: Construction Project

 

READ MORE

Refinery Pipe Rack Modules

Client: Covalent Lithium
Location: Covalent Lithium Refinery, Kwinana, WA
Project Duration: 15 Months
Service Type: Detail & Manufacture. Engineer, Procure, & Supervised Labour

 

READ MORE