Client: BHP Billiton Iron Ore Pty Ltd
Location: Newman – Western Australia
Project Duration: January 2010 – September 2012
Service Type: Construction Project

SCOPE OF WORK

The Scope of Work covered the Design, Supply, Fabrication, De-Construction of existing, Installation and Commissioning of five (5) Dust Collection Systems for lines 2 & 3 of the BHP Billiton Mine Ore Handling – Mt Whaleback Operation Processing Facility.

Works consisted of:

  • Mechanical, Structural, Civil and Electrical Design.
  • Structural Design included new structures and modifications to existing structures.
  • Decommissioning of existing Dust Collection systems and Dust Disposal systems.
  • Fabrication of Structural Steel and Mechanical Equipment.
  • Site Installation of five (5) Dust Collection Systems including Civil works, Structural Steel, Mechanical Equipment and Electrical.

The dust collection systems consist of baghouse type dust collectors including exhaust fan, bag cleaning system, dirty air ductwork, discharge chutes, agglomeration or slurry disposal system, clean air duct, discharge stack, structural and civil work.

PROJECT HIGHLIGHTS

  • Baghouses and ducting designed and engineered to fit within existing infrastructure.
  • Installation of five (5) Dust Collection Systems within existing operational infrastructure.
  • Dust collectors capacities ranged from 24,156 m³/h to 84,744 m³/h.
  • 3D site scanning of existing structures for all duct routes.

BHP Newman Upgrade

Client: BHP Billiton Iron Ore Pty Ltd
Location: Newman - Western Australia
Project Duration: January 2010 – September 2012
Service Type: Construction Project

 

READ MORE

Rio Tinto Coarse Ore Stockpile Bag House

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: January 2013 – December 2013
Service Type: Construction Project

 

READ MORE

RTIO Stockyard Waterline Replacement

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: December 2014 – September 2015
Service Type: Construction Project

 

READ MORE

Upgrade Fire Hydrant System

Client: Synergy
Location: Synergy
Project Duration: March 2014 – June 2014
Service Type: Construction Project

 

READ MORE

Elizabeth Quay Jetty

Client: Simmons Global
Location: Elizabeth Quay, Perth
Project Duration: June 2015 to July 2015
Service Type: Construction Project

 

READ MORE

Refinery Pipe Rack Modules

Client: Covalent Lithium
Location: Covalent Lithium Refinery, Kwinana, WA
Project Duration: 15 Months
Service Type: Detail & Manufacture. Engineer, Procure, & Supervised Labour

 

READ MORE