Client: Covalent Lithium
Location: Covalent Lithium Refinery, Kwinana WA
Project Duration: 2015 months
Service Type: Detail & Manufacture. Engineer, Procure, & Supervised Labour

SCOPE OF WORK

Aerison were engaged to complete the shop detailing, supply, structural & pipework fabrication, electrical containment, pre-assembly, and delivery of pipe rack module structures for the Covalent Lithium Refinery.

SOLUTION

As part of this package Aerison engaged a number of initiatives to minimise construction risk and reduce critical risk activities, including stationary hydraulic vertical lifters to eliminate cranage and mobile equipment. In addition to the vertical lifters Aerison designed, fabricated, and assembled specialised structural assembly bays, allowing multiple concurrent builds complete with overhead gantry cranes. In house passivation and hydrostatic testing completed of piping, material PMI, full material, and weld traceability. Aerison expertly utilised various fabrication materials including CS, SS, Duplex, HDPE, PVDF and rubber lined totalling circa 19km.

OUTCOME

Aerison successfully delivered over 800 tonnes of Structural Steelwork for the Pipe Rack modules, on time, on budget and with quality exceeding client expectations.

Elizabeth Quay Jetty

Client: Simmons Global
Location: Elizabeth Quay, Perth
Project Duration: June 2015 to July 2015
Service Type: Construction Project

 

READ MORE

BHP Newman Upgrade

Client: BHP Billiton Iron Ore Pty Ltd
Location: Newman - Western Australia
Project Duration: January 2010 – September 2012
Service Type: Construction Project

 

READ MORE

Rio Tinto Coarse Ore Stockpile Bag House

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: January 2013 – December 2013
Service Type: Construction Project

 

READ MORE

RTIO Stockyard Waterline Replacement

Client: Rio Tinto Iron Ore
Location: Cape Lambert
Project Duration: December 2014 – September 2015
Service Type: Construction Project

 

READ MORE

Upgrade Fire Hydrant System

Client: Synergy
Location: Synergy
Project Duration: March 2014 – June 2014
Service Type: Construction Project

 

READ MORE

Refinery Pipe Rack Modules

Client: Covalent Lithium
Location: Covalent Lithium Refinery, Kwinana, WA
Project Duration: 15 Months
Service Type: Detail & Manufacture. Engineer, Procure, & Supervised Labour

 

READ MORE