Kwinana bulk terminal shutdown

Fremantle Ports

Field Services

Project Delivery

Maintenance

Resource Sector Projects

Shutdowns

Situation

Aerison recently supported Fremantle Ports during the shutdown of the Kwinana Bulk Terminal KBB2 jetty, ensuring critical maintenance was completed efficiently and on time.

Solution

The scope included:

  • Replace filter bags and pulse valves on the AL05 Ship Unloader dust collector, the primary emissions control for the machine.
  • Perform maintenance on an additional dust collector while AL05 underwent cleaning.

Key Highlights

  • Successfully replaced all filter bags and pulse valves in the AL05 Ship Unloader Dust Collector, ensuring it was restored to optimal performance.
  • Carried out filter bag replacements on a second dust collector, maintaining operational readiness during AL05 servicing.
  • Collaborated closely with Fremantle Ports personnel to address project-specific requirements.

Outcome

The project outcomes included:

  • AL05 unit restored ahead of schedule, creating a smooth handover for subsequent shutdown crews.
  • Interim dust collector maintenance was delivered within the agreed timeframe, reflecting strong teamwork and coordination.